The Renovation Process

Five stages, each with a defined end point. What gets decided, what gets paid, and who is responsible at every step.

Every Mid-Island Renovation Group project runs through 5 stages: design and feasibility, permits and approvals, contract and schedule, build and site management, then deficiency and handover. Payments follow completed stages rather than a calendar, and the British Columbia Builders Lien Act requires an owner to retain a 10 percent holdback, releasable 55 days after the certificate of completion is issued. Permit applications go to the Town of Ladysmith, the City of Parksville, the Town of Qualicum Beach, or the Regional District of Nanaimo, depending on the address. Published BC figures put a full renovation at 7 to 14 months from the start of design to occupancy.

Most renovation disputes are not about workmanship. They are about a scope nobody wrote down, a payment schedule tied to dates instead of completed work, and a change process that was invented halfway through the job. The five stages below exist to remove those three failure modes before construction starts. Construction itself is carried out by an established Mid-Island renovation contractor working to the scope and schedule agreed at stage three.

The five stages

  1. Design and feasibility

    The existing building gets measured and documented as built. A structural review establishes what can be removed and what has to be engineered, and on pre-1990 construction a qualified person inspects for hazardous materials, as section 20.112 of the BC Occupational Health and Safety Regulation requires before demolition or renovation begins. On unserviced property, septic capacity is confirmed here. The output is a scope and a cost range built from drawings rather than from a square-foot multiplier. Published BC guidance puts design and permitting together at roughly 8 to 20 weeks.

  2. Permits and approvals

    The application goes to the authority that governs the address — the Town of Ladysmith, the City of Parksville, the Town of Qualicum Beach, or the Regional District of Nanaimo for Cedar and Nanoose Bay. Where a development permit area applies, that permit runs alongside the building permit; the regional district's Coastal Flood Hazard Development Permit Area, adopted 10 September 2024, covers Electoral Areas A, E, G and H. Only Qualicum Beach publishes a processing target, at three to four weeks for a complete residential application. The other three publish none, so the schedule treats permitting as a variable rather than a fixed block.

  3. Contract and schedule

    Fixed scope, a payment schedule tied to completed stages, and a written change-order process agreed before anyone starts. Industry practice in British Columbia caps the signing deposit at about 10 percent, and a demand well above 20 percent is worth questioning. This is also the stage to confirm whether the project crosses BC Housing's substantial reconstruction threshold — 25 percent or less of the original structure above the foundation remaining, or 75 percent or more of the finished home being new — because past that line the project is a new home and requires a licensed residential builder and 2-5-10 home warranty insurance.

  4. Build and site management

    Structure, then mechanical, then insulation, then finishes, with an inspection gating each transition. Nothing gets closed in ahead of the inspection covering it. Changes are priced and signed before the work proceeds rather than reconciled at the end. Site protection, dust control and the sequence of trades are managed as part of the schedule, not left to whoever arrives first.

  5. Deficiency and handover

    A deficiency list is built by walking the finished work, then cleared before final payment. The Builders Lien Act gives lien claimants 45 days to file, and the 10 percent holdback is releasable 55 days after the certificate of completion is issued. Signed lien releases from subtrades are worth having in hand before the final payment leaves.

How payments are staged

Payments follow completed stages, not dates on a calendar. The pattern is a signing deposit capped at around 10 percent, progress payments released against work that has actually been completed and inspected, a payment at substantial completion, and a final payment after the deficiency list is cleared. Running above that on the deposit puts the homeowner's money ahead of the work, which is the position the Builders Lien Act holdback exists to prevent.

What the homeowner is responsible for

Four things sit with the owner rather than the contractor. Section 20.112 of the BC Occupational Health and Safety Regulation places the duty to ensure a hazardous materials inspection on the owner as well as on the employers doing the work. The Builders Lien Act requires the owner to retain the 10 percent holdback. WorkSafeBC advises obtaining a clearance letter for each contractor, because an owner can be held jointly liable for unpaid WorkSafeBC premiums — the letters are free. And decisions with long lead times, particularly cabinetry, tile and fixtures, need to land on schedule or the sequence stalls behind them.

What the schedule realistically looks like

Published BC figures put a full gut renovation at 7 to 14 months from the start of design to occupancy, a mid-range whole-home renovation at 5 to 9 months, and cosmetic work at 8 to 16 weeks. Design and permitting account for roughly 8 to 20 weeks of that, and only one of the four authorities on this corridor publishes a processing target. Established contractors commonly book 6 to 12 months ahead, so the practical start date for a project scoped this autumn is often the following year.

What to ask about a contractor's project photos

Photographs are the easiest part of a contractor's website to fake and the hardest to verify, so a few questions are worth asking. Ask whether the photographs are of that company's own completed work. Ask for the before images, not just the after — the before is what shows the scope. Ask which projects had permits, and with which authority, since a permit record is independently verifiable. And ask to speak with the owners of two projects of comparable scope and budget, which is the reference that actually predicts how a $250,000 job will go.

Where the process applies: whole-home renovations and home additions.

The process starts at stage one. The questionnaire covers scope, budget, timeline and property in about two minutes.

Project inquiry

Tell Mid-Island Renovation Group about the project

Five questions covering scope, budget, timeline and property. Enough to establish whether a project is a fit before anyone books a site visit.

Step 1 of 5
What kind of project is being planned?

Pick the closest match. Scope often overlaps, and the details field at the end is there for anything that does not fit neatly.